DATE |
GENERAL DESCRIPTION
OF REPORT |
OFFICE
RESPONSIBLE |
|
02/02/12 |
Architectural Field Report #1 - Site
Preparation, Demolition |
CP Arch |
|
02/08/12 |
Architectural Field Report #2 -
Utility Line Conflicts, Demolition |
CP Arch |
|
02/16/12 |
Architectural Field Report #3 -
Gas line re-routing in progress, prep for abatement, window
paint removal testing |
CP Arch |
|
02/23/12 |
Architectural Field Report #4 -
Excavations for spread footings, Gas line re-routing still in progress,
1st Floor Education abated |
CP Arch |
|
03/01/12 |
Architectural Field Report #5 -
Excavation for elevator pit, Gas line re-routing, Forming
for grade beams, Prep for Exterior Exit Stair |
CP Arch |
|
03/08/12 |
Architectural Field Report #6 -
Forming for elevator pit walls & grade beams, Prep for Exterior Exit Stair |
CP Arch |
|
03/15/12 |
Architectural Field Report #7 -
Gas line re-routing still being investigated, Compacting
fill between grade beams, Prep for Exterior Exit Stair |
CP Arch |
|
03/22/12 |
Architectural Field Report #8 -
Gas line re-routing finalized - awaiting Entergy work, Grade beams
and foundations for Exterior Exit Stair complete, New walls
at stair forming |
CP Arch |
|
03/29/12 |
Architectural Field Report #9 -
Gas line awaiting Entergy work, new walls
at stair poured & slab-on-grade prep begun, under-slab
electrical rough-in |
CP Arch |
|
04/05/12 |
Architectural Field Report #10 -
Gas line awaiting new piping & Entergy work, new walls
stair poured & slab-on-grade prep underway, under-slab
electrical & plumbing rough-in complete |
CP Arch |
|
04/12/12 |
Architectural Field Report #11 -
HP Gas Line installed, slab-on-grade poured, exterior stair
brick infill, Sanctuary Building slate roof repair |
CP Arch |
|
04/19/12 |
Architectural Field Report #12 -
Gas regulators & attic routing being completed, exterior stair
brick infill complete, Sanctuary Building slate roof repair
ongoing |
CP Arch |
|
04/26/12 |
Architectural Field Report #13 -
Gas line awaiting Entergy, awaiting steel for new addition,
new exterior stair installed, Sanctuary Building slate roof repair
complete except for tie-in |
CP Arch |
|
05/02/12 |
Architectural Field Report #14 -
Gas line still awaiting Entergy, awaiting steel for new addition,
new exterior stair painted |
CP Arch |
|
05/10/12 |
Architectural Field Report #15 -
Gas line still awaiting Entergy, awaiting steel for new addition,
new exterior stair door, Fellowship Hall work underway |
CP Arch |
|
05/17/12 |
Architectural Field Report #16 -
Gas line still awaiting Entergy, steel for new addition -
05/21,
new exterior stair door awaiting hardware, Fellowship Hall
overhead work in progress |
CP Arch |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|