University Presbyterian Church Renovations - Baton Rouge, Louisiana

   FIELD REPORT LOG
   Last Update:
17 May 2012 15:16 Central Time


DATE GENERAL DESCRIPTION OF REPORT OFFICE RESPONSIBLE
02/02/12 Architectural Field Report #1 - Site Preparation, Demolition CP Arch
02/08/12 Architectural Field Report #2 - Utility Line Conflicts, Demolition CP Arch
02/16/12 Architectural Field Report #3 - Gas line re-routing in progress, prep for abatement, window paint removal testing CP Arch
02/23/12 Architectural Field Report #4 - Excavations for spread footings, Gas line re-routing still in progress, 1st Floor Education abated CP Arch
03/01/12 Architectural Field Report #5 - Excavation for elevator pit, Gas line re-routing, Forming for grade beams, Prep for Exterior Exit Stair CP Arch
03/08/12 Architectural Field Report #6 - Forming for elevator pit walls & grade beams, Prep for Exterior Exit Stair CP Arch
03/15/12 Architectural Field Report #7 - Gas line re-routing still being investigated, Compacting fill between grade beams, Prep for Exterior Exit Stair CP Arch
03/22/12 Architectural Field Report #8 - Gas line re-routing finalized - awaiting Entergy work, Grade beams and foundations for Exterior Exit Stair complete, New walls at stair forming CP Arch
03/29/12 Architectural Field Report #9 - Gas line awaiting Entergy work, new walls at stair poured & slab-on-grade prep begun, under-slab electrical rough-in CP Arch
04/05/12 Architectural Field Report #10 - Gas line awaiting new piping & Entergy work, new walls stair poured & slab-on-grade prep underway, under-slab electrical & plumbing rough-in complete CP Arch
04/12/12 Architectural Field Report #11 - HP Gas Line installed, slab-on-grade poured, exterior stair brick infill, Sanctuary Building slate roof repair CP Arch
04/19/12 Architectural Field Report #12 - Gas regulators & attic routing being completed, exterior stair brick infill complete, Sanctuary Building slate roof repair ongoing CP Arch
04/26/12 Architectural Field Report #13 - Gas line awaiting Entergy, awaiting steel for new addition, new exterior stair installed, Sanctuary Building slate roof repair complete except for tie-in CP Arch
05/02/12 Architectural Field Report #14 - Gas line still awaiting Entergy, awaiting steel for new addition, new exterior stair painted CP Arch
05/10/12 Architectural Field Report #15 - Gas line still awaiting Entergy, awaiting steel for new addition, new exterior stair door, Fellowship Hall work underway CP Arch
05/17/12 Architectural Field Report #16 - Gas line still awaiting Entergy, steel for new addition - 05/21, new exterior stair door awaiting hardware, Fellowship Hall overhead work in progress CP Arch